Since my last post, we have had a few different things go on.
The bricks have been cleaned. The roof ridge caps were cemented in.
Weve now got electrical cables, aswell as phone, data and tv cables.
The Air Con unit in the roof cavity, as well as the ducting has been installed.
Today we had the carpenters back who removed the bracing, did a frame tidy up and also installed the 2 sliding door cavities, as well as the 2 bases for the vanities in the bathroom and ensuite.
We also had the insulation delivered.
Tomorrow will see the eaves go on aswell as the insulation. Hopefully we might see delivery of the Gyprock  tomorrow and then some Gyprock started on Wednesday.

Air con unit in roof:


Bathroom vanity base:

Ensuite cavity for sliding door & vanity base:

Kitchen-Laundry cavity for sliding door:

Soundscreen acoustic insulation batts:

Wall & ceiling insulation batts: